Montrose-Nucla-Cahone transmission upgrade project

Montrose-Nucla-Cahone transmission upgrade project

The power system in Southwest Colorado relies on a limited network of generation and transmission infrastructure to maintain reliability and meet member load. In 1995, Tri-State and other regional utilities recognized that the transmission system was becoming stressed and new lines needed to be built and existing lines needed to be replaced or upgraded. Tri-State studied multiple ways to address the aging infrastructure, improve reliability and meet significant new demand in the region. Related studies showed the need to rebuild the existing Nucla-Sunshine transmission line and upgrade the Montrose-Nucla-Cahone (MNC) infrastructure from 115kV to 230kV to increase capacity. In 2012, Tri-State completed the Nucla-Sunshine line.

In 2011, Tri-State formally began the process to make infrastructure improvements to MNC and upgrade the capacity from 115kV to 230kV. Tri-State continues to work through the process, which includes review by several state and federal agencies.

 

FAQ

 

Contact us

info@MNCUpgrade.com or by mail or phone

 

Project updates

Right of Way improvements, access improvements, pad construction and tree clearing will be April 2017 through August 2017 on the Montrose-Nucla segment of the transmission line. Transmission line construction activities will occur between September 2017 and October 2018.

Final Environmental Assessment Issued September 2, 2016

Update 10-17-2016

The Montrose-Nucla-Cahone Transmission Improvement Project Final Environmental Assessment (EA) prepared under the National Environmental Policy Act (NEPA) with the Bureau of Land Management (BLM) as the lead federal agency and the U.S. Forest Service (USFS) as the cooperating agency was released on September 2, 2016.

The BLM and the USFS completed the Final EA based on input received during a public comment period on the draft EA that was conducted from November, 3 2015 through December 3, 2015. Both agencies are using the Final EA to make independent decisions related to the approval of the proposed project to construct, operate and maintain a transmission line through their respectively administered lands.

The Forest Service has issued a Decision Notice and Draft Finding of No Significant Impact (FONSI) concurrent with the Final EA. Based upon review of the EA and the supporting documents, the Forest Supervisor has determined that the Alternative A – Proposed Action (Selected Alternative), with the Environmental Protection Measures and stipulations (Appendix D and associated appendices of EA) of the project, is not a major federal action and will not significantly affect the quality of the human environment individually or cumulatively with other actions in the general area.

This decision is subject to a pre-decisional objection process which continues until October 24, 2016. If no objections are registered, the Forest Service Decision will become final.

The BLM will not issue a Decision Record and ROW grants until the conclusion of the USFS pre-decisional objection period.

Tri-State has completed county permitting activities with Montrose and started the application process in San Miguel and Dolores counties. County permits will enable Tri-State to construct the project and are anticipated from the two remaining counties by February 2017.

 

Environmental Assessment Under Review by BLM and USFS

Updated 8-3-2016

The Montrose-Nucla-Cahone Transmission Improvement Project is being evaluated under the National Environmental Policy Act (NEPA) with the Bureau of Land Management (BLM) as the lead federal agency and the U.S. Forest Service (USFS) as the cooperating agency. The process started in May 2014 and is expected to be completed by the end of 2016. The BLM and the USFS are currently preparing the Final Environmental Assessment (EA) based on input received during a public comment period on the draft EA that was conducted from November, 3 2015 through December 3, 2015. The Final EA is expected to be issued in late August. Both agencies will use the Final EA to make independent decisions related to the approval of the proposed project to construct, operate and maintain a transmission line through their respectively administered lands.

Tri-State has initiated county permitting activities with Montrose, San Miguel and Dolores counties. County permits will enable Tri-State to construct the project and are anticipated from all three counties by the end of 2016.